2023 Street Full Depth Reclamation (C.P. 23-17)

Update 5/26/23- In Phase 1, the base was paved and the gate valves were raised. Next week, the irons will be raised in Phase 1. In Phase 2, curb was saw-cut and removed. Curb will be poured in Phase 2 the following week.

Update 5/19/23- In Phase 1, street has been reclaimed and graded. Next week Phase 1 will be paved. In Phase 2, irons were lowered this week and next week curb will be removed.

Update 5/12/23- In Phase 1, new curb and pedestrian ramps have neem installed. Reclamation began this week and is expected to be completed the following week. The access material will be hauled off, and will begin to tolerance the road. In Phase 2, all gate valved have been exposed and filled with gravel for residents to pass over.

Update 5/5/23- In Phase 1, all gate vales have been exposed and filled with gravel for residents to pass over. Next week, curb will be saw-cut and removed, and new curb will be installed. In Phase 2, gate valves began this week, and the goal is to finish them all next week.

Update 4/28/23- All curb has been marked for removal and gate valves have been marked to be exposed. Phase 1 will commence the following week, with the curb being saw-cut and the gate valves starting to be exposed and filled with gravel for residents to pass over.

Update 4/20/23 - A project update letter will be mailed to all residents within the project today.  Construction will be phased from south to north, with Phase 1 beginning the first week of May.  For a map of how the project will generally be phased and approximate timeframes click here.

Update 4/14/23 - Manholes and valves have been marked on the project. Next week, the curb will be marked for removal and there will be some preliminary survey work done.

Update 4/12/23 - The construction contract has been awarded to North Valley Inc. Preconstruction meeting has been scheduled for April 24th. Schedule of construction will be determined at that time. After the preconstruction meeting, the project and contact information will be sent out to residents. Refer to this site for updates during the construction.

Curb, manholes, and valves will be identified for removal or modification on the project.

Identified in the City 2023-2027 Capital Improvement Plan is a full depth reclamation repaving of 6.5 miles of City streets. When roadways are deteriorated past the viable point of a mill and overlay, full depth reclamation or reconstruction is proposed. A full depth reclamation is expected to prolong the life of the roadways 30+ years before a complete reconstruction would be considered.

Full depth reclamation projects would include grinding up the existing pavement section and construction a new 3" bituminous roadway. Existing concrete curb and gutter would remain in place with very limited replacement where warranted. Also included would be minor utility repairs.

The areas identified for full depth reclamation in 2023 include: Foxberry Farms, Jonathan Woods, Oak Bluff 2nd Addition, Hartfiels Estates, Sharons 2nd Addition, Fox Woods, and Winslow Hills 1st, 2nd and 3rd Additions.

Areas identified for a full depth reclamation are depicted in blue hatch on the attached map (Click here).

25% of the project costs are proposed to be assessed to properties fronting the improvements. The remaining 75% of the project costs will be funded through the Citys Road and Bridge Fund. Residents in these areas will be invited by mail to a neighborhood informational meeting by mail this fall.

For questions related to this project please contact Jason Law at 763-767-5130 or David Berkowitz 763-767-5133.